MSIB 24-20 Upper Delaware River Dredging through 2/1/21

Back to Alert Page

MSIB 24-20 Upper Delaware River Dredging through 2/1/21

Dredging operations will be conducted by the dredge SEVENSON and the dredge BERING SEA.

Dredge BERING SEA will begin work on the red side of the channel at the northern limit of Church Channel and work downstream into Riverview Range. Upon completion of the initial work assignment, dredge BERING SEA will be moved to the northern limit of Kinkora Range and continue to work upriver into Newbold Range. 

Dredge SEVENSON will begin work in the northern part of Florence Range and work upriver into Kinkora Range.